题目

卖方已完成全部工作,但买方对最终付款有争议。合同要求仲裁。项目经理应当:
A seller has completed all work but the buyer disputes final payment. The contract requires arbitration. The project manager should:

选项

  1. A.Pay the seller immediately
  2. B.Follow the contract's dispute resolution process
  3. C.Sue the seller
  4. D.Ignore the dispute
正确答案:B

解析

解析:合同本身就约定了争议解决机制,按约定程序走才能同时保护双方与项目利益。 Rationale:Contracts define dispute resolution; following the agreed process protects both parties and the project.