题目
卖方已完成全部工作,但买方对最终付款有争议。合同要求仲裁。项目经理应当:
A seller has completed all work but the buyer disputes final payment. The contract requires arbitration. The project manager should:
选项
- A.Pay the seller immediately
- B.Follow the contract's dispute resolution process
- C.Sue the seller
- D.Ignore the dispute
解析
解析:合同本身就约定了争议解决机制,按约定程序走才能同时保护双方与项目利益。
Rationale:Contracts define dispute resolution; following the agreed process protects both parties and the project.
同考点练习题
-
PMP202611-020 · 答案 B
-
PMP202611-061 · 答案 B
-
PMP202611-121 · 答案 C
-
PMP202611-179 · 答案 B
-
PMP202611-235 · 答案 A
-
PMP202611-296 · 答案 A
-
PMP202611-310 · 答案 C
-
PMP202611-340 · 答案 C