能力缺口与培训 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-443

题目

一位刚取得 PMP 认证的项目经理被雇主指派管理一个自己毫无经验领域的项目,担心能否交付。按 PMI 道德准则,最恰当的做法是什么?
A newly PMP-certified project manager is asked by their employer to manage a project in a domain they have no experience in. They are concerned about their ability to deliver. What is the most appropriate action according to PMI's Code of Ethics?

选项

  1. A.Decline the project: taking on unfamiliar domain work risks the project's success.
  2. B.Accept the project while honestly disclosing the domain knowledge gap to the employer, identify subject matter experts to supplement the gap, develop a personal learning plan for the domain, and manage the project with appropriate humility and support structures.
  3. C.Accept the project and learn on the job, the PMP certification qualifies them for any project.
  4. D.Accept the project but do not disclose the knowledge gap to avoid appearing unqualified.
正确答案:B

解析

解析:B 正确。PMI 道德准则要求对自己的资质诚实,同时鼓励专业成长。恰当做法是接受挑战(项目管理技能可迁移),同时坦承领域缺口并积极补位——在职业诚信与专业发展之间取得平衡。宣称对任何领域都胜任(C)是不诚实的夸大;因保守而拒绝成长机会(A)过于消极;隐瞒缺口(D)直接违反诚实要求。 Rationale:B is correct. PMI's Code of Ethics requires honesty about one's qualifications while also promoting professional growth. The correct approach is to accept the challenge, project management skills are transferable, while being transparent about the domain gap and taking active steps to address it. This balances professional integrity with professional development. Claiming universal domain competence (C) is dishonest overstatement. Declining growth opportunities (A) is overly conservative. Concealing the gap (D) directly violates PMI's honesty requirement.