Scrum 事件与仪式 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-437

题目

团队刚完成新产品的第 1 个冲刺。评审显示增量可用但用户体验令人困惑。产品负责人想在第 2 冲刺加入 5 个体验改进故事,而团队产能已满。正确应对是什么?
A team has just completed sprint 1 of a new product. The sprint review shows the increment is working but the UX is confusing to users. The PO wants to add 5 new UX improvement stories to sprint 2. The team is already at capacity. What is the correct response?

选项

  1. A.Add the UX stories to the product backlog, reprioritise them appropriately alongside other backlog items during sprint planning, and commit to as many as capacity allows: letting priority and team capacity determine the sprint 2 commitment.
  2. B.Add all 5 UX stories and push lower-priority items to sprint 3.
  3. C.Ignore the UX feedback for now: the product is functionally working.
  4. D.Ask the team to work overtime in sprint 2 to accommodate the UX improvements.
正确答案:A

解析

解析:A 正确。冲刺评审的反馈本来就应转化为新的待办事项,这正是敏捷应有的运作方式。体验改进应加入待办并正确排序,再由冲刺计划决定哪些能进本轮。产品负责人不能把故事硬塞进已满负荷的冲刺(B);无视用户反馈(C)违背敏捷的客户协作原则;让团队加班(D)违反可持续节奏,也没系统性解决产能问题。 Rationale:A is correct. Sprint review feedback generates new backlog items, which is exactly how agile is supposed to work. UX improvements should be added to the backlog and prioritised properly. Sprint planning then determines which items fit within the team's capacity. The PO cannot simply add stories to an already capacity-committed sprint (B). Ignoring user feedback (C) violates agile's customer collaboration principle. Overtime (D) violates sustainable pace and doesn't address the capacity issue systematically.

同考点练习题