项目经理正在实施范围确认。客户审阅交付物后表示技术上没问题,但要求在正式验收前增加若干增强项。项目经理应该怎么做?
A project manager is performing Validate Scope. The customer reviews a deliverable, says it is technically correct but asks for several enhancements before formal acceptance. What should the project manager do?
选项
- A.Implement one or two minor enhancements informally to show goodwill.
- B.Refuse to implement enhancements, the deliverable meets the agreed scope.
- C.Seek formal acceptance of the deliverable as-is (since it is technically correct per scope), then raise a change request for the requested enhancements so they can be evaluated and approved through proper change control.
- D.Implement the enhancements immediately to secure acceptance.
解析
解析:C 正确。技术合格且符合约定范围的交付物应先行正式验收;增强诉求属于新范围,必须走变更控制。把验收与新范围混在一起,会模糊基准,还会开下“验收时可无流程扩范围”的先例。立即实现(D)放弃筹码且绕过变更控制;一概拒绝(B)不近人情,客户需求是合理的,应走正规流程解决;私下做(A)造成不受控的范围蔓延。
Rationale:C is correct. A technically correct deliverable should be formally accepted: it meets the agreed scope. Enhancement requests are new scope and must go through change control. Mixing acceptance with new scope requests creates baseline confusion and sets a precedent that scope can be expanded at acceptance without formal process. Implementing immediately (D) gives up leverage and bypasses change control. Refusing entirely (B) is unhelpful: the customer's needs are valid and should be addressed through proper process. Informal implementation (A) creates uncontrolled scope creep.