题目
项目挣值数据:BAC 80 万美元,PV 40 万,EV 44 万,AC 38 万。项目状态如何,ETC 是多少?
A project is tracking the following EVM data: BAC = $800,000, PV = $400,000, EV = $440,000, AC = $380,000. What is the project's status and what is the ETC?
选项
- A.On schedule, on budget. ETC = $400,000
- B.Behind schedule, over budget. ETC = $360,000
- C.Ahead of schedule, under budget. ETC = (BAC − EV) ÷ CPI = $360,000 ÷ 1.16 ≈ $311,000
- D.Ahead of schedule, over budget. ETC = $420,000
解析
解析:C 正确。SV = EV − PV = 44 − 40 = +4 万(进度提前);CV = EV − AC = 44 − 38 = +6 万(低于预算);CPI = 44 ÷ 38 ≈ 1.16,SPI = 44 ÷ 40 = 1.10。按当前 CPI 推算 ETC =(BAC − EV)÷ CPI =(80 − 44)÷ 1.16 ≈ 31.1 万美元。项目状态良好:进度提前且低于预算。
Rationale:C is correct. SV = EV − PV = 440 − 400 = +$40K (ahead of schedule). CV = EV − AC = 440 − 380 = +$60K (under budget). CPI = 440 ÷ 380 ≈ 1.16, SPI = 440 ÷ 400 = 1.10. ETC at current CPI = (BAC − EV) ÷ CPI = (800 − 440) ÷ 1.16 ≈ $311K. The project is performing well: ahead of schedule and under budget.