成本估算与估算责任 · PMP 练习题解析

成本管理 困难 Process 过程域 题号 PMP202611-435

题目

CFO 问敏捷项目的项目经理:“这个项目总共要花多少钱?”项目已完成 4 个冲刺,估计还有 16 个。最诚实且有用的回答是什么?
A project manager working in an agile context is asked by the CFO: "How much will this project cost in total?" The project is 4 sprints in with 16 more estimated. What is the most honest and useful answer?

选项

  1. A.Provide a range-based forecast using actual sprint cost × estimated total sprints, with upper and lower bounds reflecting velocity variance, and explain that the estimate will tighten with each sprint as more data is collected.
  2. B.Refuse to give a total: agile projects cannot be costed upfront.
  3. C.Give the original upfront estimate from the project proposal.
  4. D.Provide the total cost of the 4 completed sprints only. That is what is certain.
正确答案:A

解析

解析:A 正确。CFO 需要财务预测,敏捷团队必须用真实实证数据给出。4 个冲刺的实际成本足以算出合理的“每冲刺成本”,乘以预计总冲刺数并给出波动上下界,就是可信的区间预测。它比原始提案(C)更准,因为基于真实数据。拒绝预测(B)无用,在高层面前也不可接受;只报已发生的沉没成本(D)没有回答问题。 Rationale:A is correct. CFOs need financial forecasts: agile teams must provide them using actual empirical data. Four sprints of actual cost data enables a reasonable cost-per-sprint calculation. Multiplying by estimated total sprints (with variance bounds) gives a credible range forecast. This is more accurate than the original proposal (C) because it uses real data. Refusing to forecast (B) is unhelpful and unacceptable at the executive level. Only reporting sunk costs (D) doesn't answer the question asked.