题目
产品负责人有 3 个高价值故事(各 8 点)和 6 个中等价值故事(各 3 点),团队速率每冲刺 20 点。按加权最短作业优先(WSJF)思路,通常应优先哪类故事?
A product owner has 3 high-value stories estimated at 8 points each, and 6 medium-value stories estimated at 3 points each. The team's velocity is 20 points per sprint. Using Weighted Shortest Job First (WSJF) thinking, which type of stories should generally be prioritised?
选项
- A.The high-value stories first: highest value always wins.
- B.The medium-value stories: complete more stories per sprint.
- C.Split the sprint 50/50 between both types for balance.
- D.WSJF prioritises the ratio of value-to-cost (value ÷ effort). If medium stories deliver value per point faster than high-value stories, they should be sequenced earlier: WSJF optimises flow of value delivery, not just absolute value.
解析
解析:D 正确。WSJF(SAFe 概念)按价值/成本比排序:单位投入产出价值最高的事项优先。3 点的中等价值故事,其每点价值可能高于 8 点的高价值故事,从而带来更好的经济流动。WSJF 把延迟成本、用户/业务价值、时间关键性与风险降低之和除以工作规模。纯按价值排序(A)忽略投入;按故事数量(B)忽略价值;人为对半(C)不是有原则的排序。
Rationale:D is correct. WSJF (a SAFe concept) prioritises by value-to-cost ratio: the job delivering the most value per unit of effort goes first. A medium-value story at 3 points may deliver value faster per point than a high-value story at 8 points, creating better economic flow. WSJF considers cost of delay, user/business value, time criticality and risk reduction divided by job size. Pure value ranking (A) ignores effort. Story count (B) ignores value. Arbitrary balance (C) is not principled prioritisation.