Scrum 角色与职责 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-415

题目

组织高层想用水瀑项目那套 KPI(按时、按预算、按范围交付)来衡量敏捷团队的成功。这种做法的问题在哪?
An organisation's leadership wants to measure the success of their agile teams using the same KPIs used for waterfall projects (on-time delivery, on-budget, scope delivered). What is the problem with this approach?

选项

  1. A.Waterfall KPIs measure conformance to an upfront plan. They penalise agile teams for doing exactly what agile is designed to do (adapting scope and priorities based on learning). Agile success should be measured by customer value delivered, time-to-market, user adoption and business outcomes.
  2. B.Agile teams cannot be measured: their work is too unpredictable.
  3. C.Agile teams should be measured on velocity only.
  4. D.No problem: these are universal project success metrics.
正确答案:A

解析

解析:A 正确。这是组织敏捷化的关键概念。瀑布 KPI 奖励“按计划交付”:敏捷团队若依据新认知有意调整范围,在瀑布指标下就会被判为“失败”,哪怕它正在更好地交付价值。高层必须改用成果导向的指标。敏捷团队完全可衡量(B 错),只是要用不同指标;只看速率(C)是团队内部度量,无法直接换算业务价值。 Rationale:A is correct. This is a critical organisational agility concept. Waterfall KPIs reward delivering what was planned: agile teams that intentionally change scope based on new learning will look like "failures" by waterfall metrics even when they are succeeding at delivering value. Leadership must adopt outcome-focused metrics. Agile teams are very measurable (B is wrong), just with different metrics. Velocity alone (C) is an internal team metric with no direct business value translation.

同考点练习题