管理沟通与绩效报告 · PMP 练习题解析

沟通管理 中等 Process 过程域 题号 PMP202611-416

题目

项目经理正在准备阶段关口评审:项目进度落后、成本超支,但已完成支撑下一阶段的关键基础工作。最佳汇报方式是什么?
A project manager is preparing for a gate review. The project is behind schedule and over budget but has completed critical foundational work that enables the next phase. What is the best way to present this?

选项

  1. A.Present the true status transparently, including the schedule and cost variance, root cause analysis, what foundational value has been delivered, a realistic forecast for the next phase, and a recovery plan with options for governance to review.
  2. B.Request additional budget and time before the gate review so the project enters looking healthier.
  3. C.Emphasise the foundational work completed to minimise the schedule and cost issues.
  4. D.Defer the gate review until the project recovers to an acceptable status.
正确答案:A

解析

解析:A 正确。阶段关口评审的意义正是给决策者准确信息。完整、诚实地呈现偏差、根因、已交付价值、现实预测与挽回计划,才能让治理机构做出知情决策。淡化问题(C)误导决策者;评审前抢先要资源(B)破坏关口的治理作用;推迟评审(D)使组织失去需要的检查点。 Rationale:A is correct. Gate reviews exist precisely to provide decision-makers with accurate information. A complete, honest presentation, variances, root causes, value delivered, realistic forecast AND a recovery plan, gives the governance body everything they need to make an informed decision. Minimising issues (C) misleads decision-makers. Pre-emptive resource requests (B) before the review undermines the gate's governance purpose. Deferring the gate (D) removes the governance checkpoint the organisation needs.

同考点练习题