整合管理 中等 Process 过程域 题号 PMP202611-414

题目

PMO 要求项目经理按标准模板提交周报。某项目经理觉得模板太繁琐,改用简化邮件代替。这样做有什么风险?
A PMO has asked project managers to submit weekly status reports following a standard template. A project manager finds the template too burdensome and provides a simplified email instead. What is the risk of this approach?

选项

  1. A.Inconsistent reporting makes portfolio-level analysis difficult, undermines PMO governance, and sets a precedent for bypassing standards. If the template is genuinely burdensome, the right approach is to raise this through the PMO governance process to improve the template, not bypass it unilaterally.
  2. B.The PMO may not receive enough information for basic monitoring.
  3. C.The project manager could be disciplined for non-compliance.
  4. D.No risk: effective communication is more important than template compliance.
正确答案:A

解析

解析:A 正确。PMO 标准的目的是组合层可见性与可比性,而不是官僚合规。单方面偏离破坏了这一目的,还会立下“标准可选”的先例。职业做法是照标准执行,同时通过正规渠道推动改进。组合层面影响(A)概括最全;信息不足(B)与被处分(C)虽真实,但只覆盖局部,未及系统性风险。 Rationale:A is correct. PMO standards exist for portfolio visibility and comparability, not bureaucratic compliance. Deviating unilaterally undermines these purposes and sets a precedent that standards are optional. The professional approach is to follow the standard while using proper channels to advocate for improvement. Portfolio-level impact (A) is the most comprehensive answer. Insufficient information (B) and discipline (C) are real but narrower concerns that don't capture the full systemic risk.