敏捷与预测方法论选择 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-413

题目

项目经理在为强监管行业(制药)做项目,监管方要求每个阶段关口都有完整文档,同时有人提议采用敏捷。最恰当的应对是什么?
A project manager is developing a project for a heavily regulated industry (pharmaceuticals). The regulator requires comprehensive documentation at each phase gate. An agile approach is proposed. What is the most appropriate response?

选项

  1. A.Design a hybrid approach where agile delivery practices are used within phase gates, with the documentation and validation requirements of each regulatory phase met at defined checkpoints: combining agile speed with compliance rigour.
  2. B.Use agile informally and waterfall for all external documentation.
  3. C.Use full agile and address documentation requirements at the end of each release.
  4. D.Reject agile: regulated industries cannot use agile methodologies.
正确答案:A

解析

解析:A 正确。很多强监管行业已成功采用混合方式:在阶段关口框架内使用敏捷交付实践,并满足监管要求。制药、医疗器械、金融服务都已有合规的混合模型。一概拒绝敏捷(D)放弃了迭代开发的收益;全面敏捷而忽略文档(C)带来合规风险;内外两套(B)造成“实际做的”与“文档写的”不一致。 Rationale:A is correct. Many regulated industries successfully use hybrid approaches: agile delivery practices within phase-gated frameworks that satisfy regulatory requirements. Pharmaceutical, medical device and financial services sectors have developed compliant hybrid models. Rejecting agile outright (D) loses the benefits of iterative development. Full agile ignoring documentation requirements (C) creates compliance risk. Internal/external split (B) creates two delivery realities and potential inconsistency between what was built and what was documented.

同考点练习题