财务指标与投资决策 · PMP 练习题解析

成本管理 中等 Process 过程域 题号 PMP202611-411

题目

项目经理评估某项目的内部收益率(IRR):投资 30 万美元,预计 5 年每年产生 8 万美元收益,组织的最低要求报酬率为 15%。适用什么决策标准?
A project manager is asked to evaluate the Internal Rate of Return (IRR) of a proposed project. The project requires a $300,000 investment and is expected to generate $80,000 annually for 5 years. The organisation's hurdle rate is 15%. What decision criterion applies?

选项

  1. A.Accept if IRR > hurdle rate; reject if IRR < hurdle rate.
  2. B.Accept if total returns exceed total investment.
  3. C.Accept if NPV > IRR.
  4. D.Accept if payback period < 5 years.
正确答案:A

解析

解析:A 正确。IRR 是使项目 NPV 归零的折现率。决策规则是:IRR 高于组织的最低要求报酬率,说明项目创造价值,应当接受;低于则相对其他选择在毁损价值。回收期(D)是另一项指标;拿 NPV 与 IRR 相比(C)不是决策规则;简单加总(B)忽略了货币时间价值。 Rationale:A is correct. IRR is the discount rate at which a project's NPV equals zero. The decision rule is: if IRR exceeds the organisation's hurdle rate (required minimum return), the project creates value and should be accepted. If IRR < hurdle rate, the project destroys value relative to alternatives. Payback period (D) is a separate metric. NPV vs IRR comparison (C) is not the decision rule. Simple totals (B) ignore the time value of money.

同考点练习题