题目
项目经理向高层汇报两个备选:项目 A 净现值 20 万美元但回收期 7 年;项目 B 净现值 15 万美元但回收期 2 年。关注短期业绩的领导更可能选哪个?
A project manager is presenting a project proposal to senior leadership. The project has a positive NPV of $200,000 but a payback period of 7 years. A competing project has an NPV of $150,000 but a payback period of 2 years. Which is more likely to be selected by leadership focused on short-term performance?
选项
- A.Project A: higher NPV always wins in financial decision-making.
- B.Project B, a 2-year payback period aligns better with leaders focused on short-term performance, even though the long-term NPV is lower. Different financial metrics serve different strategic perspectives.
- C.Both should be run simultaneously.
- D.Neither: both should be reanalysed with different assumptions.
解析
解析:B 正确。不同财务指标服务于不同决策情境。关注季度收益、年度考核、资本效率等短期指标的领导,会偏好回收期更短的项目,即使总 NPV 较低。项目经理必须看懂决策情境。NPV 更高(A)在长期价值创造的语境下更受青睐;同时开展(C)隐含资源无限;本题考的正是“财务选择取决于组织优先级,而不只是算术”。
Rationale:B is correct. Different financial metrics serve different decision contexts. Leadership focused on short-term performance metrics (quarterly earnings, annual reviews, capital efficiency) will prefer faster payback even at the cost of total NPV. The PM must understand the decision-making context. Higher NPV (A) is preferred in long-term value creation contexts. Both running simultaneously (C) assumes unlimited resources. The question tests understanding that financial selection depends on organisational priorities, not just arithmetic.