Scrum 事件与仪式 · PMP 练习题解析

敏捷与混合实践 简单 Process 过程域 题号 PMP202611-405

题目

某 Scrum 团队想提升测试覆盖率,提议每三个冲刺安排一个“测试冲刺”。这种做法的问题在哪?
A team using Scrum wants to improve their test coverage. They propose adding a "testing sprint" every third sprint. What is wrong with this approach?

选项

  1. A.Sprint lengths should be extended instead of adding testing sprints.
  2. B.Nothing: dedicated testing sprints improve quality systematically.
  3. C.Testing sprints are an anti-pattern. They batch quality work rather than embedding it throughout each sprint. The solution is to include testing activities within each sprint as part of the Definition of Done, using test-driven development and automated testing.
  4. D.The testing sprint frequency is wrong. It should be every second sprint.
正确答案:C

解析

解析:C 正确。“加固冲刺/测试冲刺”在 SAFe 中被明确列为敏捷反模式,多数敏捷教练文献也认为它有问题:它把测试当成一个阶段而非持续活动,在敏捷内部复制了小型瀑布。质量应通过 TDD、自动化测试与完善的完成定义嵌入每个冲刺。讨论测试冲刺的频率(D)毫无意义——做法本身就是错的。 Rationale:C is correct. "Hardening sprints" or "testing sprints" are explicitly called out as agile anti-patterns in SAFe and acknowledged as problematic in most agile coaching literature. They indicate testing is being treated as a phase rather than a continuous activity: recreating a mini-waterfall cycle within agile. Quality should be built into each sprint through TDD, automated testing and a robust DoD. The frequency of testing sprints (D) is irrelevant, the approach itself is wrong.