某敏捷团队在做最小可行产品(MVP),产品负责人列出 50 项功能,首版只能交付 15 项。产品负责人应如何确定这 15 项?
An agile team is building a minimum viable product (MVP). The Product Owner has listed 50 features. The team can deliver 15 in the first release. How should the PO determine which 15 to include?
选项
- A.Select randomly: the MVP is about speed, not feature selection.
- B.Ask the development team to select the 15 features they find most interesting.
- C.Apply value-based prioritisation: identify the minimum set of features that delivers the core user value proposition and validates the product hypothesis. Use techniques like MoSCoW, Kano model or weighted shortest job first (WSJF).
- D.Select the 15 easiest to implement to ensure on-time delivery.
解析
解析:C 正确。MVP 的选择本质是价值判断:找出能够验证核心价值假设的最小功能集,产品负责人必须严格做价值排序。只挑最容易的(D)得到的是“最小好做产品”而非最小可行产品;随机(A)放弃核心职责;开发偏好(B)与业务价值无关。MoSCoW、卡诺与 WSJF 都是这类决策的正当工具。
Rationale:C is correct. MVP selection is fundamentally about value: identifying the minimum set of features that proves the core value hypothesis. The PO must apply value-based prioritisation rigorously. Ease of implementation (D) produces a Minimum Easy Product, not a Minimum Viable one. Random selection (A) abandons the PO's core responsibility. Developer preference (B) is not aligned with business value. MoSCoW, Kano and WSJF are all legitimate prioritisation tools for this decision.