题目
项目经理查看责任矩阵时发现,某关键工作包只标了“A(问责)”,没有任何人被标为“R(负责执行)”。问题是什么,如何解决?
A project manager is using a responsibility matrix and notices that a critical work package has no one assigned as "Responsible": only an "Accountable" designation. What is the problem and solution?
选项
- A.Remove the work package from the RACI until a responsible person is identified.
- B.No problem: the Accountable person can perform the work themselves.
- C.The Accountable person should delegate the task to whoever is available.
- D.Without a Responsible assignment, no one is designated to actually do the work, only to own the outcome. Assign at least one Responsible person immediately to ensure the work package has a doer, not just an owner.
解析
解析:D 正确。RACI 中 A 是对结果负责并签认的人,R 是实际执行的人。二者可以是同一人,但若只标 A 而无 R,就没有人被明确指派动手,形成执行缺口。临时指派(C)属非正式且不可追踪;从矩阵中删除(A)并未填补缺口;若确由 A 本人执行,也必须在矩阵中明确标注(B 只是部分成立)。
Rationale:D is correct. In RACI, Accountable = owns the outcome and signs off. Responsible = does the work. They can be the same person, but if only Accountable is assigned with no Responsible, no one is explicitly tasked with actually performing the work: creating an execution gap. Ad-hoc delegation (C) is informal and untracked. Removing it from the RACI (A) doesn't address the work gap. If the Accountable person will do the work, that must be stated explicitly in the matrix (B).