资源规划与获取 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-400

题目

项目经理同时管理多个项目,资源在各项目间共享。某项目急需一名目前已投入另一项目的资源。最佳做法是什么?
A project manager is managing multiple projects simultaneously. Resources are shared across all projects. One project requires an urgent resource that is currently committed to another. What is the best approach?

选项

  1. A.Take the resource from the other project, the urgent project has higher priority.
  2. B.Ask the resource to work on both projects simultaneously to meet all needs.
  3. C.Escalate to the resource manager or PMO with both project needs documented, assess the relative priority of both projects at the portfolio level, and implement the decision with clear communication to both project teams.
  4. D.Delay the urgent project until the resource becomes available.
正确答案:C

解析

解析:C 正确。跨项目资源冲突不能由单个项目经理单方面解决,必须通过资源经理、PMO 或发起人等治理渠道在组合层面排序。两个项目的需求都要记录,决定由合适层级做出。单方面抽调(A)在无授权情况下损害另一项目;让一人兼顾(B)会同时降低两边的效能;被动延期(D)是未经确认就假定优先级。 Rationale:C is correct. Cross-project resource conflicts cannot be resolved unilaterally by one project manager. They require portfolio-level prioritisation through the appropriate governance channel (resource manager, PMO or sponsor). Both projects' needs must be documented and the decision made at the right level. Unilaterally taking resources (A) damages the other project without proper authority. Multi-tasking across projects (B) reduces effectiveness on both. Passive delay (D) assumes priority without validation.