敏捷与混合实践 简单 Process 过程域 题号 PMP202611-401

题目

某 Scrum 团队的完成定义包含:代码完成、单元测试、代码评审、集成测试、文档更新。有成员认为文档拖慢节奏,主张从完成定义中去掉。应该怎么处理?
A Scrum team's Definition of Done includes: code complete, unit tested, code reviewed, integration tested, and documentation updated. A team member argues that documentation slows them down and should be removed from the DoD. What should happen?

选项

  1. A.Discuss in the retrospective. If documentation genuinely creates disproportionate overhead without value, explore lightweight alternatives, but do not remove quality gates without understanding the downstream impact on operations, support and future development.
  2. B.The team must keep the DoD unchanged: any modification weakens quality standards.
  3. C.Remove documentation from the DoD: working software is more important than documentation per the Agile Manifesto.
  4. D.Make documentation optional: let each team member decide per story.
正确答案:A

解析

解析:A 正确。完成定义应当被质疑和改进,但要在回顾会中、在充分理解后果的前提下进行。敏捷宣言说的是“可运行软件高于面面俱到的文档”,并非“不要文档”。完成定义代表最低质量标准。去掉文档看似加快交付,却会在下游产生运维故障、支持负担与知识流失等成本。团队应评估文档是否真的过重,或能否做得更轻更快。 Rationale:A is correct. The DoD should be challenged and improved, but through the retrospective with full understanding of consequences. The Agile Manifesto says "working software over comprehensive documentation", not "no documentation." The DoD represents minimum quality. Removing documentation may seem to speed delivery but creates downstream costs (operational failures, support burden, knowledge loss). The team should evaluate whether documentation is truly heavyweight or whether it can be made lighter and faster.