团队正在为 SAFe 的 PI 计划会做准备。下列哪项是 PI 计划成功最关键的输入?
A team is preparing for PI Planning in SAFe. Which of the following is the most critical input to successful PI Planning?
选项
- A.Fully estimated team backlogs for each sprint in the PI.
- B.A clear, prioritised Program Backlog with a defined Program Vision and business context, so teams understand what they are planning toward and can make meaningful capacity and dependency decisions.
- C.A completed risk register for all identified programme-level risks.
- D.Velocity data from the previous PI for all teams.
解析
解析:B 正确。缺少清晰愿景与已排序的项目群待办,是 PI 计划失败最常见的原因:不了解战略方向与优先工作,团队就无法对做什么、管哪些依赖、怎么分配产能做出有意义决定。冲刺级完整估算(A)是在 PI 计划会中产出,而非会前准备;风险登记册(C)与速率数据(D)是有用输入,但重要性次于愿景与待办清晰度。
Rationale:B is correct. PI Planning without a clear vision and prioritised program backlog is the most common cause of PI Planning failure. Teams cannot make meaningful decisions about what to build, which dependencies to manage or how to allocate capacity without understanding the strategic direction and prioritised work. Full sprint-level estimates upfront (A) are developed during PI Planning, not before it. Risk registers (C) and velocity data (D) are useful inputs but secondary to the vision and backlog clarity.