高层要求某敏捷团队承诺未来 12 个月的固定功能路线图且不允许变更。这种做法最大的风险是什么?
An agile team is asked by leadership to commit to a specific feature roadmap for the next 12 months with no changes allowed. What is the most significant risk of this approach?
选项
- A.Team velocity will decrease under the pressure of a fixed commitment.
- B.A fixed 12-month feature commitment prevents the team from responding to market changes, user feedback or strategic shifts: delivering planned features that may no longer be valuable while excluding newly urgent ones.
- C.The team may not be able to estimate that far in advance accurately.
- D.The product backlog will become too large to manage effectively.
解析
解析:B 正确。敏捷的核心价值主张是适应性:依据当前认知交付最有价值的东西。冻结 12 个月的功能清单会把团队变成“功能工厂”,按计划而非按需要造东西;在快速变化的市场中这会造成巨大浪费。估算精度(C)确实是问题但次要;待办规模(D)属管理问题;速率影响(A)属推测,也不是最大风险。
Rationale:B is correct. Agile's core value proposition is adaptability, the ability to deliver what is most valuable given current knowledge. A frozen 12-month feature list creates "feature factories" that build what was planned rather than what is needed. In fast-moving markets, this produces significant waste. Estimation accuracy (C) is a real concern but secondary. Backlog size (D) is a management issue. Velocity impact (A) is speculative and not the most significant risk.