题目
团队发现近四个冲刺的周期时间(从开始做故事到交付)持续变长,而在制品限额并未变化。最可能的原因是什么?
A team notices that their cycle time (time from starting a story to delivering it) has been increasing over the last four sprints even though WIP limits haven't changed. What is the most likely cause?
选项
- A.The sprint length should be increased to accommodate longer cycle times.
- B.WIP limits should be increased to allow more work to flow through simultaneously.
- C.The team is getting slower due to low morale.
- D.Story complexity is increasing (stories are getting larger), hidden dependencies are emerging, or quality issues requiring rework are accumulating: all causing items to spend longer in each stage.
解析
解析:D 正确。在制品限额不变而周期时间上升,说明事项在各阶段停留更久——原因通常是故事变大、隐藏依赖出现,或技术债累积导致返工。根因分析应聚焦“工作本身发生了什么变化”。士气(C)有可能但属猜测;延长冲刺(A)只是迁就症状;提高在制品限额(B)与看板的正确应对相反,只会让周期更长(利特尔法则:周期 = 在制品 ÷ 吞吐量)。
Rationale:D is correct. Rising cycle time with stable WIP limits indicates items are taking longer to move through stages: caused by increasing story complexity, undiscovered dependencies or growing technical debt requiring rework. The root cause analysis should examine what has changed about the work itself. Morale (C) is possible but speculative. Increasing sprint length (A) accommodates the symptom without fixing it. Increasing WIP limits (B) is the opposite of the correct Kanban response. It would worsen cycle time further (Little's Law: CT = WIP ÷ Throughput).