项目治理与PMO · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-390

题目

某团队首次引入敏捷,却因组织要求任何开发前必须先出详尽的前期文档而举步维艰。这属于哪类挑战?
A team adopting agile for the first time is struggling because their organisation requires detailed upfront documentation before any development can begin. What type of challenge is this?

选项

  1. A.A team skills challenge: the team needs more agile training.
  2. B.A technical challenge: the team needs better agile tools.
  3. C.An organisational impediment, the organisation's governance model conflicts with agile's iterative approach. This requires working with leadership to adapt documentation requirements to be "just enough, just in time" rather than comprehensive upfront.
  4. D.A process challenge, the team should document requirements in parallel with development.
正确答案:C

解析

解析:C 正确。这是典型的组织层面障碍:治理模式(重量级前期文档)与敏捷“恰到好处”的文档理念在结构上不兼容。Scrum Master 或敏捷教练必须在组织层面推动治理调整,而不只是在团队层面折腾。工具(B)与培训(A)解决不了治理冲突;边开发边补文档(D)可作为过渡的务实做法,但没有解决根因障碍。 Rationale:C is correct. This is a classic organisational impediment, the governance model (heavyweight upfront documentation) is structurally incompatible with agile's "just enough" documentation philosophy. The Scrum Master or agile coach must work at the organisational level to adapt governance, not just at the team level. Tools (B) and training (A) don't solve a governance conflict. Parallel documentation (D) may be a pragmatic interim solution but doesn't resolve the root impediment.