团队在开放式办公室使用实体看板,近期若干成员转为远程办公。最恰当的调整是什么?
A team uses a physical Kanban board in an open office. Several team members have recently moved to remote work. What is the most appropriate adaptation?

选项

  1. A.Ask remote workers to maintain their own separate tracking system.
  2. B.Switch to email status updates for remote team members.
  3. C.Migrate to a digital Kanban tool (e.g., Jira, Trello, Azure DevOps) that provides full visibility to all team members regardless of location, while preserving all the visual management benefits of the physical board.
  4. D.Keep the physical board: remote workers can see it via webcam.
正确答案:C

解析

解析:C 正确。敏捷工具应服务于团队需要;团队一旦分布化,实体看板就失去了“共享可视”的作用。数字化工具保留了可视化管理原则,同时人人可访问。靠摄像头看(D)无法实时更新;各自维护(A)制造两套事实源与协调成本;邮件同步(B)恰恰退回到看板本要解决的沟通问题。 Rationale:C is correct. Agile tools should serve the team's needs, when the team becomes distributed, the physical board fails its purpose of providing shared visibility. A digital tool preserves the visual management principle while making it accessible to everyone. Webcam viewing (D) is impractical for real-time updates. Separate tracking (A) creates two sources of truth and coordination overhead. Email updates (B) are a regression to the very communication problem Kanban solves.