管理团队:绩效与冲突 · PMP 练习题解析

资源管理 困难 People 人域 题号 PMP202611-384

题目

项目经理发现两名成员存在项目之前就有的私人冲突,拒绝在共同任务上合作,而项目只有一个团队。最佳做法是什么?
A project manager discovers that two team members have a personal conflict that predates the project. They refuse to work together on shared tasks. The project has only one team. What is the best approach?

选项

  1. A.Remove one team member from the project to eliminate the conflict.
  2. B.Meet with both individuals separately to understand their perspectives, then facilitate a structured conversation focused on professional collaboration expectations, not resolving the personal relationship. Set clear performance expectations and escalate to HR if they cannot maintain professional conduct.
  3. C.Allow them to resolve it themselves over time without PM intervention.
  4. D.Separate the two individuals by assigning them to tasks that never overlap.
正确答案:B

解析

解析:B 正确。既存的私人冲突要靠设定职业边界来处理,而不是试图修复私人关系。项目经理不能也不应去“调解感情”,但可以而且必须确立“无论个人感受如何都要保持职业行为”的明确期望。结构性隔离(D)只是权宜且未必可行,也回避了处理;在尚未正式提出职业行为要求前就调人(A)过度;等待自行化解(C)会让项目影响无限延续。 Rationale:B is correct. Pre-existing personal conflicts require professional boundary-setting rather than personal resolution attempts. The PM cannot and should not try to fix a personal relationship, but they can and must establish clear expectations for professional conduct regardless of personal feelings. Structural separation (D) is a partial measure that may not be possible and avoids resolution. Removal (A) is disproportionate before professional conduct has been formally addressed. Waiting for self-resolution (C) allows the project impact to continue indefinitely.

同考点练习题