题目
项目经理发现两名成员存在项目之前就有的私人冲突,拒绝在共同任务上合作,而项目只有一个团队。最佳做法是什么?
A project manager discovers that two team members have a personal conflict that predates the project. They refuse to work together on shared tasks. The project has only one team. What is the best approach?
选项
- A.Remove one team member from the project to eliminate the conflict.
- B.Meet with both individuals separately to understand their perspectives, then facilitate a structured conversation focused on professional collaboration expectations, not resolving the personal relationship. Set clear performance expectations and escalate to HR if they cannot maintain professional conduct.
- C.Allow them to resolve it themselves over time without PM intervention.
- D.Separate the two individuals by assigning them to tasks that never overlap.
解析
解析:B 正确。既存的私人冲突要靠设定职业边界来处理,而不是试图修复私人关系。项目经理不能也不应去“调解感情”,但可以而且必须确立“无论个人感受如何都要保持职业行为”的明确期望。结构性隔离(D)只是权宜且未必可行,也回避了处理;在尚未正式提出职业行为要求前就调人(A)过度;等待自行化解(C)会让项目影响无限延续。
Rationale:B is correct. Pre-existing personal conflicts require professional boundary-setting rather than personal resolution attempts. The PM cannot and should not try to fix a personal relationship, but they can and must establish clear expectations for professional conduct regardless of personal feelings. Structural separation (D) is a partial measure that may not be possible and avoids resolution. Removal (A) is disproportionate before professional conduct has been formally addressed. Waiting for self-resolution (C) allows the project impact to continue indefinitely.