敏捷与混合实践 困难 Process 过程域 题号 PMP202611-383

题目

敏捷团队在冲刺中途收到测试用户群的反馈,与当前冲刺工作方向根本冲突。产品负责人想立即转向。应该怎么处理?
An agile team receives mid-sprint feedback from a beta user group that fundamentally contradicts the direction of the current sprint work. The PO wants to immediately pivot. What should happen?

选项

  1. A.Ignore the feedback until the sprint ends: user feedback should be processed at sprint review only.
  2. B.Continue the sprint but add the new direction as additional scope within the same sprint.
  3. C.Stop all current sprint work and immediately pivot based on the user feedback.
  4. D.The PO should evaluate the feedback's significance. If it truly invalidates the sprint goal, the sprint may be cancelled and a new sprint planned. If the feedback is important but not sprint-goal-breaking, it should be added to the backlog and addressed in the next sprint.
正确答案:D

解析

解析:D 正确。Scrum 指南允许在冲刺目标失效时取消冲刺——这是罕见但正当的选项,适用于重大转向。但并非每条冲突性反馈都值得取消冲刺,产品负责人必须评估严重程度。不取消就中途转向(C、B)会破坏冲刺承诺、降低可预测性;完全忽略(A)损害敏捷的响应力,不过对非关键输入,冲刺评审本就是设计好的反馈节点。 Rationale:D is correct. The Scrum Guide allows sprint cancellation if the sprint goal becomes obsolete, a rare but legitimate option for significant pivots. However, not every piece of contradictory feedback warrants a sprint cancellation; the PO must evaluate severity. Mid-sprint pivots without cancellation (C, B) disrupt the sprint commitment and reduce predictability. Ignoring feedback entirely (A) undermines agile's responsiveness, but the sprint review is the designed feedback point for non-critical input.