题目
Scrum Master 发现某资深成员总被默认当作团队的“小经理”:指挥他人、单方面做实现决策。风险是什么,应如何应对?
A Scrum Master notices that a senior team member is always selected informally as the "mini-manager" of the team: directing others and making implementation decisions unilaterally. What is the risk and how should it be addressed?
选项
- A.Formalise the senior member's leadership role to make the hierarchy explicit.
- B.The risk is a pseudo-hierarchy that undermines self-organisation and disengages less senior members. The Scrum Master should facilitate discussions about self-organisation, ensure all team members have voice in decisions, and coach the senior member to mentor rather than direct.
- C.No risk: senior team members naturally take leadership and this improves efficiency.
- D.Remove the senior member from the team to restore balance.
解析
解析:B 正确。敏捷团队里的隐性层级会压制自组织所需的心理安全:资历浅的人一旦觉得自己的意见无关紧要,就不再提想法。Scrum Master 的职责是维护扁平、自组织的团队动力。辅导资深成员从“替别人做决定”转向“分享知识与提问”,能把其专长变成团队资产而非瓶颈。把层级正式化(A)正是 Scrum 明确要避免的;把人移出(D)浪费专长且过度。
Rationale:B is correct. Informal hierarchies in agile teams suppress the psychological safety needed for self-organisation. Junior members stop contributing ideas when they feel their input is irrelevant. The Scrum Master's role is to preserve the flat, self-organising team dynamic. Coaching the senior member to mentor (share knowledge, ask questions) rather than direct (make decisions for others) converts their expertise into a team asset rather than a bottleneck. Formalising the hierarchy (A) creates what Scrum explicitly avoids. Removal (D) wastes expertise and is disproportionate.