Scrum 角色与职责 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-373

题目

某成员在每日站会上说:“我被卡住了——等法务的决定已经 3 天,无法推进。”Scrum Master 当下的职责是什么?
A Scrum team member raises during daily standup: "I'm blocked: I'm waiting on a decision from the legal team for 3 days and can't proceed." What is the Scrum Master's immediate responsibility?

选项

  1. A.Tell the team member to follow up with the legal team themselves.
  2. B.Reassign the blocked task to another team member who is not blocked.
  3. C.Note the blocker and address it in the next sprint retrospective.
  4. D.Take ownership of removing the impediment immediately after the standup: escalate to the appropriate contact in the legal team, set a response deadline, and unblock the team member as fast as possible.
正确答案:D

解析

解析:D 正确。清除团队自身无法控制的障碍是 Scrum Master 的首要职责。已卡 3 天,正在消耗冲刺产能,必须立刻升级。站会负责暴露障碍,Scrum Master 在会后立即行动。等到回顾会(C)会让障碍吃掉整个冲刺;把事退给成员(A)否定了 Scrum Master 的障碍清除职能;转派(B)没有消除障碍,且未必可行。 Rationale:D is correct. Removing impediments that are outside the team's control is the Scrum Master's primary responsibility. A 3-day blocker is already costing sprint capacity: immediate escalation is required. The standup surfaces blockers; the Scrum Master acts on them right after. Waiting for a retrospective (C) allows the blocker to consume the entire sprint. Passing back to the team member (A) negates the Scrum Master's impediment-removal role. Reassignment (B) doesn't remove the blocker and may not be possible.