题目
某成员在每日站会上说:“我被卡住了——等法务的决定已经 3 天,无法推进。”Scrum Master 当下的职责是什么?
A Scrum team member raises during daily standup: "I'm blocked: I'm waiting on a decision from the legal team for 3 days and can't proceed." What is the Scrum Master's immediate responsibility?
选项
- A.Tell the team member to follow up with the legal team themselves.
- B.Reassign the blocked task to another team member who is not blocked.
- C.Note the blocker and address it in the next sprint retrospective.
- D.Take ownership of removing the impediment immediately after the standup: escalate to the appropriate contact in the legal team, set a response deadline, and unblock the team member as fast as possible.
解析
解析:D 正确。清除团队自身无法控制的障碍是 Scrum Master 的首要职责。已卡 3 天,正在消耗冲刺产能,必须立刻升级。站会负责暴露障碍,Scrum Master 在会后立即行动。等到回顾会(C)会让障碍吃掉整个冲刺;把事退给成员(A)否定了 Scrum Master 的障碍清除职能;转派(B)没有消除障碍,且未必可行。
Rationale:D is correct. Removing impediments that are outside the team's control is the Scrum Master's primary responsibility. A 3-day blocker is already costing sprint capacity: immediate escalation is required. The standup surfaces blockers; the Scrum Master acts on them right after. Waiting for a retrospective (C) allows the blocker to consume the entire sprint. Passing back to the team member (A) negates the Scrum Master's impediment-removal role. Reassignment (B) doesn't remove the blocker and may not be possible.
同考点练习题
-
PMP202611-064 · 答案 B
-
PMP202611-084 · 答案 C
-
PMP202611-094 · 答案 D
-
PMP202611-122 · 答案 B
-
PMP202611-163 · 答案 B
-
PMP202611-169 · 答案 B
-
PMP202611-255 · 答案 B
-
PMP202611-290 · 答案 A