团队建设与团队章程 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-372

题目

项目经理新加入组织,接手一个已完成 30% 的项目。团队看起来有能力但投入度低。前两周应优先做什么?
A project manager is new to the organisation and inherits a project that is already 30% complete. The team appears capable but disengaged. What should the project manager prioritise in the first two weeks?

选项

  1. A.Immediately change the project approach to signal new leadership.
  2. B.Focus on the project schedule and cost status before addressing team dynamics.
  3. C.Meet individually with team members to understand their perspectives, identify the source of disengagement and build relationships, then review documentation alongside this engagement.
  4. D.Review all project documentation to understand the technical status fully before engaging with the team.
正确答案:C

解析

解析:C 正确。有能力却不投入的团队既是最宝贵的资产,也是当下最紧迫的风险。一对一沟通能揭示不投入源于上一任领导失败、方向不清、未解决的冲突还是个人因素,同时建立有效领导所需的信任。只看文档(D)必要但不充分;不了解背景就改做法(A)可能更糟;先抓进度成本(B)是在治标而不碰根因。 Rationale:C is correct. A disengaged capable team is the most valuable asset and the most urgent risk simultaneously. Individual conversations reveal whether disengagement stems from previous leadership failure, unclear direction, unresolved conflict or personal factors, and build the trust needed for the PM to lead effectively. Documentation review (D) is necessary but insufficient if the human issues aren't addressed. Immediate changes (A) without understanding the context risk making things worse. Schedule/cost focus (B) treats symptoms while the root cause goes unaddressed.