沟通技巧:倾听反馈与情商 · PMP 练习题解析

沟通管理 中等 Process 过程域 题号 PMP202611-374

题目

项目经理与供应商谈判,认为对方报价偏高。按 PMI 原则,最有效的谈判方式是什么?
A project manager is negotiating with a vendor who is proposing a price that the project manager believes is inflated. What is the most effective negotiation approach according to PMI principles?

选项

  1. A.Counter with the lowest possible offer to anchor the negotiation at the extreme.
  2. B.Focus on interests rather than positions: understand what drives the vendor's pricing, share the project's constraints, and work toward a fair outcome that meets both parties' core needs.
  3. C.Accept the price to maintain the vendor relationship for future projects.
  4. D.Threaten to go to a competitor to create urgency for price reduction.
正确答案:B

解析

解析:B 正确。PMI 与 Fisher/Ury 的原则性谈判(《谈判力》)都强调以利益为基础的谈判优于立场式讨价还价。理解供应商的深层利益,往往能找到付款条件、范围调整、批量承诺等创造性方案,双方都能满足。极端锚定(A)是立场手段,可能损害关系;威胁(D)制造对抗;无条件接受(C)把价值拱手让人。 Rationale:B is correct. PMI and Fisher/Ury's principled negotiation (Getting to Yes) both emphasise interest-based negotiation over positional bargaining. Understanding the vendor's underlying interests often reveals creative solutions (payment terms, scope adjustment, volume commitment) that satisfy both parties. Extreme anchoring (A) is a positional tactic that can damage relationships. Threats (D) create adversarial dynamics. Accepting without challenge (C) leaves value on the table.