敏捷与混合实践 困难 Process 过程域 题号 PMP202611-361

题目

组织正从瀑布转向敏捷,高层管理者担心失去可见性与控制力。最好的应对方式是什么?
An organisation is transitioning from waterfall to agile. Senior managers are concerned about losing visibility and control. What is the best way to address this concern?

选项

  1. A.Reassure managers that loss of some control is necessary for agile to work.
  2. B.Maintain waterfall reporting structures alongside agile delivery to satisfy management.
  3. C.Show managers the sprint burn-down charts every day to maintain visibility.
  4. D.Demonstrate that agile provides MORE visibility: working software at every sprint review, transparent impediment boards, velocity trends and outcome metrics give managers richer real-time information than milestone reports.
正确答案:D

解析

解析:D 正确。对失控的担忧是敏捷落地中常见且可以理解的心理。正确做法不是否定,而是重新框定:敏捷通过可运行软件演示、透明的团队看板与实证指标,提供更频繁、更有意义的可见性。每天报燃尽图(C)会变成微管理;双套报告(B)增加负担与混乱;只说“必须放弃控制”(A)等于印证其恐惧而没有给出解法。 Rationale:D is correct. The concern about losing control is a common and understandable resistance to agile adoption. The correct response is not to dismiss it but to reframe it: agile actually provides more frequent, meaningful visibility through working software demonstrations, transparent team boards and empirical metrics. Daily burn-downs (C) create micromanagement. Dual reporting (B) creates overhead and confusion. Telling managers control loss is necessary (A) confirms their fear without providing a solution.