范围控制与变更处理 · PMP 练习题解析

范围管理 困难 Process 过程域 题号 PMP202611-360

题目

有人要求项目经理加入一个只对某个部门有利、在组织层面缺乏商业理由的功能,且项目商业论证中并不包含该功能。项目经理应该怎么做?
A project manager is asked to include a feature that benefits only one department and has no organisational-level business justification. The project's business case does not include this feature. What should the project manager do?

选项

  1. A.Ask the department to fund the feature separately through a different project.
  2. B.Include the feature to maintain the department's support for the project.
  3. C.Include the feature informally so it doesn't appear in the project scope documentation.
  4. D.Raise a formal change request. If the feature cannot be justified against the project's business case and organisational objectives, it should not be added, even if it has departmental support.
正确答案:D

解析

解析:D 正确。所有范围变更都需走正式变更请求,并对照商业论证与目标评估。缺乏组织层面论证的功能不应加入——商业论证决定项目为何存在、交付什么。无理由加入就是范围蔓延;偷偷加入(C)更糟,形成无文档、无批准的隐性范围;建议另立资金(A)或许可行,但当下的动作是走变更控制。 Rationale:D is correct. All scope changes require a formal change request evaluated against the project's business case and objectives. A feature with no organisational justification should not be added, the business case governs what the project exists to deliver. Including it without justification is scope creep. Adding it informally (C) is worse. It creates hidden scope with no documentation or approval. Suggesting separate funding (A) may be appropriate but the immediate action is to follow change control.

同考点练习题