题目
项目同时含敏捷与预测型部分,项目经理正在编制相关方参与计划。记录参与策略的最佳做法是什么?
A project manager is developing a stakeholder engagement plan for a project with both agile and predictive components. Which approach is best for documenting stakeholder engagement strategies?
选项
- A.Skip formal documentation, use ad-hoc engagement since hybrid projects are complex enough without additional plans.
- B.Create a detailed stakeholder engagement plan upfront and follow it throughout the project.
- C.Use separate engagement plans for the agile and predictive components.
- D.Create an initial stakeholder engagement plan that covers both delivery streams, and build in regular review points to update engagement strategies as stakeholder needs, project context and relationship dynamics evolve.
解析
解析:D 正确。混合环境下的相关方参与计划必须是“活文档”,因为敏捷部分会不断产生新信息,改变相关方需求与预期。覆盖两条交付流的统一计划加内置评审节奏,既提供结构又保留适应性。前期定死(B)无法适应敏捷节奏;两套计划(C)易造成不一致;不做文档(A)会导致关键相关方的参与被遗漏。
Rationale:D is correct. Stakeholder engagement plans in hybrid environments need to be living documents, especially because agile components generate frequent new information that changes stakeholder needs and expectations. An integrated plan (covering both streams) with built-in review cadence provides structure while maintaining adaptability. A rigid upfront plan (B) won't survive contact with an agile delivery rhythm. Separate plans (C) risk creating inconsistency. No documentation (A) leads to ad-hoc engagement with key stakeholders falling through the gaps.