题目
组织想把敏捷扩展到 8 个团队,共同开发同一个产品。各团队单独跑冲刺运转良好。首要挑战是什么,应如何应对?
An organisation wants to scale agile across 8 teams working on the same product. Individual team sprints are well-functioning. What is the primary challenge and how should it be addressed?
选项
- A.Each team should maintain a separate product backlog to preserve autonomy.
- B.Combine all 8 teams into one large Scrum team for unified delivery.
- C.Velocity will decrease when teams work on the same product, keep them on separate products.
- D.Cross-team dependency management and integration is the primary challenge. Frameworks like SAFe, LeSS or Nexus provide structures (e.g., PI Planning, Scrum of Scrums) to coordinate multiple teams on one product.
解析
解析:D 正确。规模化敏捷的首要挑战是跨团队依赖管理——单个团队表现好是必要条件但不充分。SAFe、LeSS、Nexus 等框架正是为解决这一点而存在。分做不同产品(C)是回避规模化而非解决;同一产品各自独立待办(A)会造成方向分裂;合并成一个大团队(B)会破坏小团队的认知效率(Scrum 团队理想规模 3~9 人)。
Rationale:D is correct. Scaling agile introduces cross-team dependency management as the dominant challenge: individual team performance is necessary but insufficient. Scaled frameworks (SAFe, LeSS, Nexus) exist specifically to address this. Separate products (C) avoids scaling rather than addressing it. Separate backlogs (A) for one product creates divergence. Combining into one large team (B) destroys the cognitive effectiveness of small teams (optimal Scrum team size is 3–9).