题目
某敏捷团队的产品开发进行到中途,竞争对手发布了类似产品,显著改变了市场预期。产品负责人想彻底转向产品方向。应该怎么做?
An agile team is midway through a product development effort. A competitor releases a similar product that changes market expectations significantly. The Product Owner wants to pivot the product direction entirely. What should happen?
选项
- A.Continue the current plan: pivoting mid-project wastes the investment made so far.
- B.Complete the current release and then pivot for the next one.
- C.Terminate the project since the original business case is now invalid.
- D.Embrace the pivot: agile is designed for exactly this scenario. The PO should update the product vision and backlog, the team should be briefed on the new direction, and the pivot should be executed in the next sprint.
解析
解析:D 正确。“响应变化高于遵循计划”是敏捷宣言的第四条价值观。能依据市场反馈转向,是敏捷交付的核心竞争优势。此前的沉没成本与决策无关——沿错误方向继续代价更大。延续原计划(A)把过去投入置于未来价值之上;若产品概念在新方向仍可行,终止(C)为时过早;先做完本次发布(B)无谓延迟了转向。
Rationale:D is correct. Responding to change over following a plan is the fourth Agile Manifesto value. The ability to pivot based on market feedback is a core competitive advantage of agile delivery. The sunk cost of previous work is irrelevant: continuing the wrong direction costs more. Continuing the original plan (A) prioritises past investment over future value. Termination (C) is premature if the product concept is still viable in a new direction. Completing the current release (B) delays the pivot unnecessarily.