活动排序与网络图 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-351

题目

项目经理正在编制项目进度:任务 A 必须完成,任务 B 才能开始;任务 B 必须完成,任务 C 才能开始。这属于哪种依赖类型?
A project manager is preparing a project schedule. Task A must finish before Task B can start. Task B must finish before Task C can start. This is an example of which type of dependency?

选项

  1. A.Start-to-Start (SS)
  2. B.Finish-to-Start (FS)
  3. C.Finish-to-Finish (FF)
  4. D.Start-to-Finish (SF)
正确答案:B

解析

解析:B 正确。完成—开始(FS)是最常见的依赖类型:前置任务必须先完成,后续任务才能开始。“A 完成后 B 才能开始”就是典型的 FS 关系。SS(A)表示两项任务同时开始;FF(C)表示两项任务必须同时完成;SF(D)最罕见,表示前置任务要等后续任务开始后才能完成。 Rationale:B is correct. Finish-to-Start (FS) is the most common dependency type: the predecessor must FINISH before the successor can START. "A must finish before B can start" is a textbook FS relationship. Start-to-Start (A) means both tasks start together. Finish-to-Finish (C) means tasks must finish at the same time. Start-to-Finish (D) is the rarest, the predecessor cannot finish until the successor starts.