题目
项目经理用控制图监控项目。若干数据点都落在控制限内,但连续 7 个点全部位于均值之上。这说明什么?
A project manager is monitoring a project using a control chart. Several data points are within the control limits but form a continuous run of 7 points all above the mean. What does this indicate?
选项
- A.The process is trending positively: no action needed.
- B.Only upper or lower control limit breaches require investigation.
- C.A run of 7 consecutive points on one side of the mean indicates a non-random pattern (the "Rule of Seven"), the process is out of control and requires investigation even though points are within limits.
- D.The process is in control since all points are within the control limits.
解析
解析:C 正确。“七点规则”是质量控制的关键概念:连续 7 个数据点落在均值同一侧,即便没有点越限,也说明存在非随机(可归属)原因。随机波动应大致对称分布于均值上下。出现七连点意味着过程发生了系统性偏移,需要调查。在有七点规则适用时,仅“点都在限内”(D、B)并不等于过程受控。
Rationale:C is correct. The "Rule of Seven" is a key quality control concept: seven consecutive data points on one side of the mean indicate a non-random (assignable) cause even if no points breach the control limits. Random variation produces roughly equal distribution above and below the mean. A run of seven suggests a systematic shift in the process that needs investigation. Being within limits (D, B) does not mean the process is under control if the Rule of Seven applies.