题目
产品待办已完成梳理,前 30 个故事都有估算。冲刺计划时团队发现其中 3 个最高优先级的故事缺少验收标准。团队应该怎么做?
A product backlog has been refined and the top 30 stories are estimated. During sprint planning, the team finds that 3 of the top-priority stories have missing acceptance criteria. What should the team do?
选项
- A.Commit to all stories and ask the PO to clarify requirements as work progresses.
- B.Do not commit to stories without acceptance criteria: work with the PO during planning to define them, or replace these stories with ready alternatives from the backlog.
- C.Skip the stories and pull in lower-priority items that are fully defined.
- D.Commit to the stories and define acceptance criteria during the sprint.
解析
解析:B 正确。没有验收标准的故事不算“就绪”,无法有意义地估算、承诺或测试。就绪定义(无论显式还是隐含)都要求有验收标准。团队应在计划期间与产品负责人快速补齐,或改拉已就绪的替代项。无标准就承诺(D、A)会导致实现偏差和评审被拒;直接跳到低优先级(C)则无谓地放弃了优先级顺序。
Rationale:B is correct. A story without acceptance criteria is not "ready". It cannot be meaningfully estimated, committed to or tested. The Definition of Ready (implicit or explicit) requires acceptance criteria. The team should either define them with the PO during planning (if quick) or pull in ready alternatives. Committing without criteria (D, A) leads to misaligned implementation and sprint review rejections. Simply skipping to lower-priority items (C) abandons the priority order unnecessarily.