某团队用计划扑克估算一个故事,给出 2、3、13、3、2。其中 13 来自最有经验的开发人员。接下来应该怎么做?
A team using Planning Poker estimates a story. Estimates are: 2, 3, 13, 3, 2. The outlier (13) is from the most experienced developer. What should happen next?
选项
- A.Accept the experienced developer's estimate of 13 since they know best.
- B.The outlier should explain their reasoning. They may have identified complexity others missed. The team discusses and re-estimates until consensus is reached.
- C.Average all estimates: (2+3+13+3+2) ÷ 5 = 4.6, round to 5.
- D.Use the majority estimate of 3 since four team members agree.
解析
解析:B 正确。计划扑克的目的就是暴露分歧、引发讨论。离群值尤其来自资深开发时,是有价值的信号——他可能发现了别人漏掉的依赖、技术风险或隐藏复杂度。揭示离群值后的讨论正是该技术的真正价值所在。取平均(C)丢掉了信号;多数表决(D)压制了重要知识;盲目接受高估算(A)跳过了这场学习性对话。
Rationale:B is correct. The purpose of Planning Poker is to surface disagreement and generate discussion. An outlier, especially from an experienced developer, is a valuable signal. They may have identified a dependency, technical risk or hidden complexity that others missed. The discussion that follows the outlier reveal is where the real value of the technique lies. Averaging (C) discards the signal. Majority rule (D) silences important knowledge. Blindly accepting the high estimate (A) skips the learning conversation.