合同类型与条款 · PMP 练习题解析

采购管理 中等 Process 过程域 题号 PMP202611-345

题目

项目经理要在固定总价加激励费用(FPIF)合同与工时材料(T&M)合同之间选择,用于一项周期较长、存在一定不确定性的开发合作。哪种更合适,为什么?
A project manager is selecting between a Fixed Price Incentive Fee (FPIF) contract and a Time and Materials (T&M) contract for a long development engagement with some uncertainty. Which is more appropriate and why?

选项

  1. A.T&M: it is always better because it places risk on the buyer.
  2. B.T&M: uncertainty always makes fixed price inappropriate.
  3. C.FPIF. It motivates the seller to control costs while sharing risk, making it appropriate when scope is reasonably defined but some uncertainty exists. T&M would be better for very uncertain or short-term engagements.
  4. D.FPIF: it removes all risk from the buyer.
正确答案:C

解析

解析:C 正确。FPIF 设有最高限价(为买方风险设顶)、包含激励卖方控成本的机制,并通过分成比例提供弹性,适合作“范围大体明确但有一定不确定性”的情形。T&M 把全部成本风险放在买方,更适合极短期或高度不确定的工作。T&M 并非总是更优(A),它消除了成本效率激励;只要存在不确定性就排除固定价变体(B)不成立;FPIF 仍是风险共担,并未消除买方敞口(D)。 Rationale:C is correct. FPIF provides a ceiling price (capping buyer risk), an incentive for the seller to control costs, and flexibility through the sharing ratio. It is well-suited for "reasonably defined scope with some uncertainty" scenarios. T&M places all cost risk on the buyer and is best for very short or highly uncertain work. T&M is not always better (A). It removes incentive for cost efficiency. Uncertainty alone doesn't rule out fixed-price variants (B). FPIF still shares risk. It doesn't eliminate buyer exposure (D).