项目章程与立项 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-330

题目

项目经理正在筹划项目启动会,参会者 25 人、来自三个部门。启动会最重要的成果是什么?
A project manager is planning a project kickoff meeting with 25 attendees across three departments. What is the most important outcome to achieve from the kickoff?

选项

  1. A.Present the risk register to ensure all risks are known from day one.
  2. B.Formally assign tasks to all 25 attendees during the meeting.
  3. C.Distribute the project schedule so all team members know their deadlines.
  4. D.Establish shared understanding of project objectives, scope, roles, responsibilities and success criteria, and build the initial team cohesion needed to work effectively together.
正确答案:D

解析

解析:D 正确。启动会的首要目的是对齐与建队:让所有人明白项目走向、自己在其中的角色、成功如何衡量。这个共同基础能防止执行期偏离。分发进度计划(C)、评审风险(A)、分派任务(B)都服务于“形成统一、有动力、方向一致团队”这一根本目标之下的次要事项。 Rationale:D is correct. The primary purpose of a project kickoff is alignment and team formation: ensuring everyone understands where the project is going, their role in it and how success will be measured. This shared foundation prevents misalignment throughout execution. Schedule distribution (C), risk review (A) and task assignment (B) are all secondary to the fundamental goal of creating a unified, motivated, aligned team.