Scrum 角色与职责 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-327

题目

冲刺回顾会上,团队认为结对编程能提升代码质量,但会暂时降低速率。产品负责人因速率影响而反对。Scrum Master 应该怎么做?
In sprint retrospective, the team identifies that pair programming would improve code quality but would temporarily reduce velocity. The Product Owner opposes it due to the velocity impact. What should the Scrum Master do?

选项

  1. A.Side with the PO: velocity directly impacts delivery commitments and takes priority.
  2. B.Override the PO: technical practices are the team's domain and the PO has no authority over them.
  3. C.Implement pair programming immediately and explain the velocity impact after the next sprint.
  4. D.Facilitate a conversation between the PO and team that explains the long-term quality benefits versus short-term velocity cost, and help them reach a shared decision.
正确答案:D

解析

解析:D 正确。技术实践最终属于开发团队的领域,但可持续改进需要共识。Scrum Master 的角色是促成透明对话,让产品负责人理解质量欠债会在未来以速率损失偿还,从而兼顾团队技术自主与产品负责人的交付责任。越过产品负责人(B)制造未解决的冲突;只站产品负责人(A)否定团队的专业判断;先斩后奏(C)破坏信任。 Rationale:D is correct. While technical practices are ultimately the development team's domain, sustainable improvement requires shared understanding. The Scrum Master facilitates a transparent conversation, the PO needs to understand that quality debt has future velocity costs. This respects both the team's technical autonomy and the PO's delivery accountability. Overriding the PO (B) creates conflict without resolution. Siding with the PO (A) dismisses the team's professional judgment. Surprise implementation (C) destroys trust.

同考点练习题