题目
项目经理正在协调利益对立的相关方:运营总监希望系统保持现有工作流,CTO 希望现代化并自动化。两者都是关键决策者。最佳做法是什么?
A project manager is coordinating stakeholders with opposing interests. The operations director wants the system to maintain current workflows; the CTO wants to modernise and automate. Both are key decision-makers. What is the best approach?
选项
- A.Facilitate a structured stakeholder alignment session where both parties can articulate their underlying needs, identify shared goals and negotiate a solution that addresses both perspectives.
- B.Side with the CTO since modernisation aligns with the organisation's strategic direction.
- C.Design the project to satisfy both requirements fully, regardless of scope impact.
- D.Escalate to the CEO to adjudicate the disagreement.
解析
解析:A 正确。相关方冲突中项目经理的角色是促进,而非裁决或站队。结构化会议能把深层利益摆到台面(运营总监可能要的是稳定性,CTO 要的是效率),往往能找到双方都能接受的方案。选边站(B)会疏远另一方;直接上报 CEO(D)跳过了促谈这一步;无约束地都满足(C)会导致范围失控。
Rationale:A is correct. The project manager's role in stakeholder conflicts is facilitation, not arbitration or advocacy. A structured session surfaces underlying interests (the operations director may want reliability; the CTO may want efficiency) and often reveals a solution that satisfies both. Siding with one party (B) alienates the other. CEO escalation (D) skips the facilitation step. Designing for both without constraint (C) creates unmanaged scope growth.
同考点练习题
-