题目
项目经理正在编制商业论证。项目总成本 60 万美元,预计年度收益 20 万美元。投资回收期是多少?
A project manager is preparing a business case. The total cost of the project is $600,000 and the expected annual benefit is $200,000. What is the payback period?
选项
- A.4 years
- B.2 years
- C.6 months
- D.3 years
解析
解析:D 正确。投资回收期 = 总投资 ÷ 年收益 = 600,000 ÷ 200,000 = 3 年。回收期衡量项目收益收回初始投资所需的时间,是最简单的财务评价方法之一。注意它不考虑货币时间价值,因此 NPV 与 IRR 被视为更精细的指标。
Rationale:D is correct. Payback Period = Total Investment ÷ Annual Benefit = $600,000 ÷ $200,000 = 3 years. The payback period is the time required for a project's benefits to recover its initial investment. It is one of the simplest financial evaluation methods. Note that payback period ignores the time value of money, which is why NPV and IRR are considered more sophisticated measures.