题目
一名团队成员私下告诉项目经理,另一名成员在高层相关方面前把共同工作成果算作自己的功劳。反映问题的人很不满,但不愿暴露身份。项目经理应该怎么做?
A project team member tells the project manager privately that another team member has been taking credit for shared work in front of senior stakeholders. The reporting team member is upset but does not want to be identified. What should the project manager do?
选项
- A.Raise the issue in the next team meeting to establish accountability norms.
- B.Tell the reporting team member to address it directly with the accused.
- C.Observe the situation directly and, if confirmed, address the behaviour privately with the accused team member while ensuring team contributions are recognised transparently going forward.
- D.Immediately confront the accused team member and ask them to stop.
解析
解析:C 正确。项目经理应先核实再行动,并私下处理人际问题。直接观察既保护了反映者的身份,也能确认事实;私下与被指控者沟通保全了其尊严;建立透明的贡献认可机制可防止再次发生。未经核实即对质(D)过于草率;在团队会议上公开提出(A)会暴露反映者并让被指控者当众难堪;让反映者自行解决(B)是回避项目经理的责任。
Rationale:C is correct. The PM should verify before acting and handle interpersonal issues privately. Observing directly protects the informant's identity while confirming the situation. Addressing it privately with the accused respects dignity. Implementing transparent contribution recognition prevents recurrence. Immediate confrontation (D) without verification is hasty. Raising in a team meeting (A) exposes the informant and embarrasses the accused publicly. Sending the reporter to handle it (B) avoids the PM's responsibility.