敏捷度量:速率与燃尽 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-313

题目

某 Scrum 团队想衡量自己是否在持续进步。跟踪团队效率逐冲刺改善最有用的指标是什么?
A team using Scrum wants to measure whether they are improving over time. Which metric is most useful for tracking team efficiency improvement sprint-over-sprint?

选项

  1. A.Sprint burn-down chart: shows remaining work within a single sprint.
  2. B.Number of user stories in the backlog: fewer stories means better efficiency.
  3. C.Velocity trend: tracks story points completed per sprint over multiple sprints to show whether team capacity is growing.
  4. D.Team satisfaction survey: measures morale as a proxy for efficiency.
正确答案:C

解析

解析:C 正确。跨多个冲刺的速率趋势是跟踪团队效率改善的标准敏捷指标,速率上升说明团队更高效。冲刺燃尽图(A)只反映单冲刺内进展,体现不出长期改善;满意度调查(D)有价值,但衡量的是状态而非效率;待办规模(B)反映范围,不代表团队绩效。 Rationale:C is correct. Velocity trend over multiple sprints is the standard agile metric for tracking team efficiency improvement. A rising velocity trend indicates a team is becoming more effective. The sprint burn-down (A) shows within-sprint progress but doesn't track improvement over time. Satisfaction surveys (D) are valuable but measure wellbeing, not efficiency directly. Backlog size (B) reflects scope, not team performance.