组织的项目组合评审委员会决定终止某项目,因为竞争对手推出的产品使原商业论证失效。项目已完成 60%。项目经理应该怎么做?
An organisation's portfolio review board decides to terminate a project because a competitor has released a product that makes the business case obsolete. The project is 60% complete. What should the project manager do?
选项
- A.Continue the project independently and present the completed product to management.
- B.Immediately stop all work and release resources without documentation.
- C.Execute an orderly project closure: finalise deliverables to a logical stopping point, document lessons learned, release resources, archive project records, and ensure all contractual obligations are met.
- D.Argue for project continuation since 60% completion represents significant sunk cost.
解析
解析:C 正确。项目因战略原因终止时,项目经理的责任是有序收尾,而不是对抗决定。沉没成本与未来决策无关(沉没成本谬误)。规范收尾包括文档、经验教训、资源释放与合同管理。据理力争(D)无视项目组合委员会的权限;无序急停(B)带来合同与知识流失风险;擅自继续(A)违反治理。
Rationale:C is correct. When a project is terminated for strategic reasons, the PM's responsibility is an orderly closure, not to fight the decision. Sunk costs are irrelevant to future decisions (the sunk cost fallacy). Proper closure includes documentation, lessons learned, resource release and contract management. Arguing against the decision (D) ignores the portfolio board's authority. Immediate unstructured stop (B) creates contractual and knowledge loss risks. Continuing independently (A) violates governance.