Scrum 角色与职责 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-311

题目

某敏捷项目临近发布,团队已完成计划功能的 80%。产品负责人希望以现有功能立即发布,而不是等剩下 20%。哪项原则支持这个决定?
An agile project's release is approaching. The team has delivered 80% of the planned features. The Product Owner wants to release now with the available functionality rather than wait for the remaining 20%. What principle supports this decision?

选项

  1. A.The Scrum Sprint Review: checking work at the end of each sprint.
  2. B.The Agile Manifesto principle of delivering working software frequently and prioritising customer value over comprehensive feature completion.
  3. C.The MoSCoW method: must-have features were delivered so others can be deferred.
  4. D.Risk avoidance: releasing early reduces the risk of delivering nothing.
正确答案:B

解析

解析:B 正确。敏捷宣言第二条原则明确提出“频繁交付可运行的软件”,并把“尽早、持续交付有价值的软件使客户满意”列为最高优先级。已含高优先级功能的 80% 先发布,优于等 100%。冲刺评审(A)是仪式而非原则;风险规避(D)是次要理由;MoSCoW(C)是排序技术,不是这里的根本原则。 Rationale:B is correct. The Agile Manifesto's second principle explicitly states: "deliver working software frequently" and "our highest priority is to satisfy the customer through early and continuous delivery of valuable software." Releasing 80% of planned features that deliver value is better than waiting for 100%, especially if those features represent the highest-priority items. Sprint Review (A) is a ceremony, not a principle. Risk avoidance (D) is secondary. MoSCoW (C) is a prioritisation technique, not the underlying principle here.