题目
在敏捷中,产品路线图与冲刺待办有什么区别?
In agile, what is the difference between a product roadmap and a sprint backlog?
选项
- A.A product roadmap is owned by the Scrum Master; a sprint backlog is owned by the Product Owner.
- B.A product roadmap lists all features to be built; a sprint backlog lists all bugs to be fixed.
- C.A product roadmap and sprint backlog are the same thing at different levels of detail.
- D.A product roadmap is a high-level strategic view of the product direction over time; a sprint backlog is the team's committed plan for a single sprint.
解析
解析:D 正确。产品路线图是战略沟通工具,展示产品跨多个版本的演进方向,归产品负责人所有;冲刺待办是团队对当前冲刺的战术承诺,归开发团队所有。两者服务的对象与规划视野不同。路线图不是完整功能清单(B);A 把归属说反了;两者是截然不同的产物(C)。
Rationale:D is correct. The product roadmap is a strategic communication tool showing the planned evolution of the product over multiple releases: owned by the Product Owner. The sprint backlog is the team's tactical commitment for the current sprint: owned by the development team. They serve different audiences at different planning horizons. The roadmap is not a comprehensive feature list (B). Ownership is reversed in A. They are distinctly different artefacts (C).