题目
某 Scrum 团队被要求为配合营销活动,承诺 6 个月发布的固定功能集合。团队担心需求会变化。最佳做法是什么?
A Scrum team is asked to commit to a fixed set of features for a 6-month release to support a marketing campaign. The team is concerned that requirements will evolve. What is the best approach?
选项
- A.Commit to the full feature set: marketing campaigns must be supported.
- B.Refuse to commit to any features: agile does not support fixed-scope commitments.
- C.Commit to a fixed date and a prioritised minimum viable feature set, with remaining capacity used for additional features based on what is learned during delivery.
- D.Commit to the features and stop accepting new requirements until the release is complete.
解析
解析:C 正确。这是典型的敏捷发布规划场景:固定日期,承诺营销所需的最小可用功能集,其余部分保留按交付认知调整的灵活性,从而兼顾业务可预期性与敏捷适应性。承诺全部功能(A)无视学习;拒绝任何承诺(B)不现实;冻结需求(D)否定了敏捷响应变化的核心价值。
Rationale:C is correct. This is a classic agile release planning scenario. The solution is to fix the date and commit to the minimum viable feature set needed for the campaign, while keeping flexibility in what gets added beyond that. This balances business predictability with agile adaptability. A full feature commitment (A) ignores learning. Refusing all commitments (B) is impractical. Freezing requirements entirely (D) negates agile's core value of responding to change.