题目
项目经理正在实施定性风险分析。该过程的主要输出是什么?
A project manager is conducting qualitative risk analysis. Which of the following is the PRIMARY output of this process?
选项
- A.Contingency reserves calculated for the overall project.
- B.A prioritised list of risks based on probability and impact assessment.
- C.Expected Monetary Value (EMV) for each risk.
- D.Risk response strategies for all identified risks.
解析
解析:B 正确。定性风险分析通过对概率与影响的主观评估(常用概率—影响矩阵)对风险排序,其主要输出是风险优先级清单,供定量分析与风险应对规划使用。EMV(C)是定量风险分析的输出;应急储备(A)来自定量分析与应对规划;风险应对策略(D)在规划风险应对过程中制定。
Rationale:B is correct. Qualitative risk analysis prioritises risks using subjective assessment of probability and impact (often using a probability-impact matrix). Its primary output is a prioritised risk list that feeds into quantitative analysis and risk response planning. EMV (C) is an output of quantitative risk analysis, not qualitative. Contingency reserves (A) result from quantitative analysis and risk response planning. Risk responses (D) are developed in the Plan Risk Responses process.
同考点练习题
-
PMP202611-576 · 答案 D
-
PMP202611-580 · 答案 C
-
PMP202611-635 · 答案 D